SunE GLT Chuckawalla Solar, LLC
Project Size: 4.4 MW
Start of Construction: October 2011
Date of Interconnection: May 2012
Technology:
~16,000 72-cell High-Efficiency utility Poly-Si Solar Panels
Mounting Solution:
Single axis track ground mounted
Estimated Annual Power Production: 9,000,000 kWh/yr
Estimated Annual CO2 Offset: 20,000,000 lbs/yr
The Chuckwalla Project (a.k.a. ‘SunE GLT Ironwood Solar 2’ project) is a ~4.4 MW expansion to the existing 4.59 MW solar array, serving the Chuckawalla State Prison. Power is provided to the host customer under a private solar services agreement that results in a net savings to the host, every year for the life of the contract.


Start of Construction: October 2011
Date of Interconnection: May 2012
Technology:
~16,000 72-cell High-Efficiency utility Poly-Si Solar Panels
Mounting Solution:
Single axis track ground mounted
Estimated Annual Power Production: 9,000,000 kWh/yr
Estimated Annual CO2 Offset: 20,000,000 lbs/yr
The Chuckwalla Project (a.k.a. ‘SunE GLT Ironwood Solar 2’ project) is a ~4.4 MW expansion to the existing 4.59 MW solar array, serving the Chuckawalla State Prison. Power is provided to the host customer under a private solar services agreement that results in a net savings to the host, every year for the life of the contract.